Case study

Brigg Power Station

Electrical contractors for the main contractor on a 40 MW biomass plant. The project finished on schedule.

Service
Contract
Sector
Renewables
Two electricians testing switchgear in the electrical room of a power plant

The client

Brigg Power Station in Lincolnshire is a 40 MW biomass plant that runs mainly on straw.

The challenge

One of the main contractors on the site needed specialist electrical contractors with strong technical skills and a real commitment to health and safety, on a complex, working plant.

What we did

We supplied a team of qualified electrical contractors who brought:

  • panel building, relay and switchgear wiring, and containment
  • LV and HV SWA glanding and termination
  • confidence working from red and green drawings
  • careful work alongside the existing plant, to full safety standards

The outcome

The project finished on schedule.

The team met the site’s safety standards throughout and fitted the new work in with the existing equipment.

Whichever side of the hire you're on, we'll pick up.

Call 0114 349 2305, Monday to Friday, 8.30am to 4.30pm.